Huawei FusionModule1000A20 Commissioning Manual page 116

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A20:
Table of Contents

Advertisement

FusionModule1000A20 Prefabricated All-in-One
Data Center
Commissioning Guide
Figure 9-28 Emergency light
Step 2 Remove the protective cover of the emergency light.
Step 3 Remove the red pin of the emergency light. The emergency light turns on.
Figure 9-29 Removing the red pin
Step 4 Reinstall the protective cover of the emergency light.
Step 5 Insert the power plug of the emergency light.
Step 6 Press the red button of the emergency light. The emergency light turns on. When
you release the red button, the emergency light turns off.
Issue 03 (2022-12-15)
NO TE
The emergency light turns off, and the power indicator turns on.
Copyright © Huawei Digital Power Technologies Co., Ltd.
9 Commissioning Core Components
109